Heat Pump System

for 2025 Rivian EDV 500 Dual Motor AWD (EDV) · AWD
Editorial review:Chris HacklemanMaster Technician · 20+ years · Jeff MooreMaster Lexus & Toyota Mechanic · 20+ years
Difficulty
Expert
Time
3.0 h
Tools
13
Steps
14
Expert-verified. Personally reviewed and approved by OLP's master technicians (Chris Hackleman & Jeff Moore — 20+ years each). Always follow the vehicle's factory service information and torque specs.

Complete removal and replacement of the heat pump system assembly, including refrigerant recovery, component replacement, and system recharge for the Rivian EDV 500 dual motor electric vehicle.

Warnings

⚠️This vehicle operates with high voltage systems up to 800V. Ensure HV battery is disconnected and locked out before beginning work. Verify zero voltage before touching any orange-colored cables or components.
⚠️R-1234yf refrigerant is mildly flammable. Use only approved recovery equipment in a well-ventilated area. Do not expose to open flames or hot surfaces above 700°F.
⚠️Never open refrigerant system while under pressure. Always recover refrigerant using approved equipment before disconnecting lines.
EV coolant is toxic and must be properly recovered and disposed of according to local regulations. Do not mix with conventional antifreeze.
Heat pump system contains PAG oil under pressure. Wear eye protection when disconnecting refrigerant lines.
ℹ️Work must be performed by EPA-certified technicians for refrigerant handling. Certification required for R-1234yf systems.

Tools required

R-1234yf refrigerant recovery machineEssential
AC vacuum pumpEssential
Manifold gauge set (R-1234yf)Essential
Torque wrench setEssential
Electric vehicle lift points (chassis adapters)Essential
Battery disconnect toolEssential
Digital multimeterEssential
Refrigerant leak detector (electronic)Essential
Socket set (metric)Essential
Plastic pry tools
Line disconnect tools for AC fittingsEssential
Coolant drain pan (5 gallon minimum)Essential
Trim panel removal tools

Parts

  • Heat pump compressor assembly × 1 — Use OEM specification
  • Heat pump condenser/evaporator unit × 1 — Use OEM specification
  • Refrigerant line O-rings × 1 — R-1234yf compatible O-ring kit
  • PAG oil for R-1234yf system × 1 — Use OEM specification
  • R-1234yf refrigerant × 1 — Use OEM specification
  • Heat pump electrical connector seals × 1 — Use OEM specification
  • Coolant hose clamps × 4 — OEM replacement clamps
  • Underbody shield fasteners × 1 — Push-pin retainers

Fluids

  • EV Battery/Motor Coolant — 10 qt

Preparation

  1. Park vehicle on level surface and engage parking brake
  2. Access high voltage battery disconnect located in rear service panel under cargo area
  3. Remove HV battery service disconnect and install lockout device per Rivian service procedures
  4. Wait minimum 5 minutes for HV capacitors to discharge
  5. Verify zero voltage on HV system using CAT III-rated multimeter at service disconnect points
  6. Raise vehicle on lift using manufacturer-specified lift points with EV chassis adapters
  7. Remove front underbody shields and aero panels to access heat pump components
  8. Place warning tags on steering wheel indicating HV system is disabled
  9. Connect R-1234yf recovery machine to service ports on heat pump system
  10. Document initial refrigerant charge weight and system pressures before recovery

Procedure

  1. 1
    Recover refrigerant from heat pump system
    Connect manifold gauges to low and high side service ports on heat pump assembly located in front compartment. Operate refrigerant recovery machine according to manufacturer instructions until system vacuum is achieved. Recovery typically takes 15-20 minutes. Record amount of refrigerant and oil recovered for recharge calculations.
  2. 2
    Drain EV coolant from thermal management system
    Locate coolant drain valve on underbody coolant manifold near front motor assembly. Connect drain hose to valve and route to collection pan. Open drain valve and allow system to gravity drain. System capacity is 10 quarts total. Use coolant evacuation tool to pull remaining coolant from heat pump heat exchanger passages if available.
  3. 3
    Disconnect electrical connectors from heat pump components
    Locate main heat pump control module connector on driver side of heat pump assembly. Press release tab and disconnect. Disconnect compressor power connector (orange HV cable with safety interlock). Disconnect temperature sensor connectors (3 total) from heat exchanger and refrigerant lines. Disconnect pressure transducer connectors on high and low side service valves. Label all connectors for reassembly.
  4. 4
    Disconnect refrigerant lines from heat pump assembly
    Using appropriate line disconnect tools, separate refrigerant lines at quick-connect fittings. There are four main connections: suction line, discharge line, and two heat exchanger connections. Cap all open refrigerant ports immediately with shipping caps to prevent moisture ingress. Remove and discard all O-rings from fittings.
  5. 5
    Disconnect coolant lines from heat pump heat exchanger
    Release spring clamps on two coolant hoses connecting to heat pump heat exchanger using hose clamp pliers. Twist hoses to break seal and pull off fittings. Expect residual coolant spillage. Plug coolant ports on heat exchanger and vehicle-side lines with rubber plugs to prevent contamination.
  6. 6
    Remove heat pump mounting fasteners
    Remove four mounting bolts securing heat pump assembly to front subframe. Bolts are located at corners of mounting bracket. Support heat pump assembly weight with transmission jack or suitable support before removing final bolt. Assembly weighs approximately 45 pounds.
  7. 7
    Remove heat pump assembly from vehicle
    Carefully lower heat pump assembly on transmission jack while guiding electrical harness and remaining lines clear of component. Maneuver assembly forward and down to remove from vehicle. Note orientation and routing of all connections for reinstallation.
  8. 8
    Install new heat pump assembly
    Position new heat pump assembly on transmission jack and raise into position. Align mounting brackets with subframe mounting points. Guide assembly into place while ensuring no wiring or lines are pinched. Install mounting bolts hand-tight initially, then tighten in diagonal pattern. Verify assembly is seated properly against mounting surfaces.
  9. 9
    Connect coolant lines to heat pump
    Install new coolant hoses onto heat pump heat exchanger fittings. Ensure hoses are fully seated over barbed fittings. Install new spring clamps positioned 1/4 inch from hose end. Verify clamps are properly engaged and hoses cannot be pulled off by hand.
  10. 10
    Connect refrigerant lines with new O-rings
    Install new R-1234yf compatible O-rings on all refrigerant line fittings. Lubricate O-rings lightly with PAG oil specified for system. Connect refrigerant lines to heat pump assembly quick-connect fittings. Push connectors until audible click is heard and verify lock indicator shows proper engagement. Tug test each connection.
  11. 11
    Reconnect all electrical connections
    Reconnect all electrical connectors to heat pump components in reverse order of removal. Ensure each connector locks fully and seals are properly seated. Reconnect compressor HV power connector with orange cable, ensuring safety interlock is properly engaged. Reconnect control module connector, temperature sensors, and pressure transducers.
  12. 12
    Fill thermal management system with coolant
    Add 10 quarts of EV Battery/Motor Coolant through fill port on coolant reservoir. Use only coolant meeting Rivian specifications. Fill slowly to avoid air pockets. With HV system still disconnected, operate coolant pump using service mode on diagnostic tool to circulate coolant and purge air. Top off coolant as level drops during purging process.
  13. 13
    Evacuate and recharge refrigerant system
    Connect vacuum pump to service ports and evacuate system to 500 microns for minimum 45 minutes. System must hold vacuum for 30 minutes without rise to pass leak test. Add specified amount of PAG oil to match oil recovered plus replacement for new components. Charge system with R-1234yf refrigerant to specification using recovery machine in charge mode. Typical charge is 2.8-3.2 pounds but verify with service data.
  14. 14
    Perform leak test and system verification
    Use electronic refrigerant leak detector to check all connections, fittings, and component seams for leaks. Check pressure readings on manifold gauges against specifications for ambient temperature. Pressures should stabilize with system off. Reconnect HV battery service disconnect. Clear any diagnostic trouble codes using scan tool. Enable heat pump system through HVAC controls and verify operation.

Reassembly

  1. Reinstall all underbody shields and aero panels using new push-pin fasteners where needed
  2. Lower vehicle from lift and verify all tools and equipment are removed from work area
  3. Remove lockout device from HV battery service disconnect
  4. Reconnect HV battery per Rivian service procedures
  5. Remove warning tags from steering wheel

Verification

  • Start vehicle and verify no warning lights or messages related to thermal management system
  • Using Rivian diagnostic tool, verify heat pump system operates in all modes (heating, cooling, defrost)
  • Check coolant level in reservoir after system has reached operating temperature and top off if needed
  • Verify refrigerant pressures are within specification during operation using manifold gauges
  • Test cabin heating and cooling performance at maximum and minimum temperature settings
  • Perform electronic leak detection recheck after system has operated for 10 minutes
  • Verify all electrical connectors show proper communication with no DTCs stored
  • Check for coolant leaks at heat exchanger connections after thermal cycling
  • Verify compressor engages and disengages smoothly without abnormal noise or vibration
  • Document final refrigerant charge weight and system operating pressures in service records
🔧Stuck on this heat pump system? Take it to The Diag Desk.A human with 20+ years in the bay answers about YOUR Rivian within 24 hours — never AI. $25, and you're not charged unless you get an answer.Ask a tech →

More procedures for this vehicle

🔧 Database maintained under the daily editorial review of Chris Hackleman · Master Technician · 20+ years and Jeff Moore · Master Lexus & Toyota Mechanic · 20+ years. Spot an error? Use the Help link above — a human reads every report.
Stuck on this repair? Take it to The Diag Desk — ask a master tech about this exact car → real human answer within 24h, never AI
⚠ STILL BEHIND THE PAYWALL
The 2025 Rivian EDV 500 repair data is incomplete because no one has sponsored it yet. For $99, we generate the full step-by-step procedures, then fact-check them with a second AI pass and your expert review. Your name on every procedure, permanently.
The same data would cost $169/mo from Mitchell1 or $30/year from ALLDATAdiy — and you'd be renting access, not freeing it. Sponsor once, free forever.
Sponsor the Rivian EDV 500 — $99 →
Building an app?
Free API access to all this data — 50 requests/day, no card required.
Get an API key →
Run a shop?
Manage repairs, estimates, and customers with ShopBase — $249/mo, all features included.
Try ShopBase →