✓Fact-checked. Built from OLP's spec database, then independently fact-checked line by line with every correction applied. Master-tech sign-off by Chris Hackleman is queued. Cross-check torque values against the factory manual, and stop if anything looks unsafe. How our data is made.
This procedure covers the removal and replacement of the onboard charger module in a 2023 Chevrolet Bolt EUV, including high-voltage system de-energization and component access.
Warnings
⚠️This procedure involves high-voltage components (up to 400V DC). Failure to properly de-energize the system can result in severe injury or death. Only qualified technicians should perform this work.
⚠️Wait minimum 10 minutes after disconnecting the high-voltage system before touching any orange cables or connectors. Capacitors may retain lethal charge.
⚠️Always verify zero voltage with a multimeter before proceeding with disassembly.
⚠The onboard charger weighs approximately 30 lbs. Use proper lifting technique or assistance.
⚠Do not allow metal tools or objects to contact high-voltage terminals simultaneously.
Tools required
Insulated high-voltage toolsEssential
Torque wrench (5-30 Nm range)Essential
As an Amazon Associate and Autel/ANCEL partner, OLP earns from qualifying purchases — how we link. This never changes the specs we publish.
Parts
- Onboard charger module × 1 — Use OEM specification
- High-voltage connector seals (if damaged) × 1 — Use OEM specification
As an Amazon Associate and Autel/ANCEL partner, OLP earns from qualifying purchases — how we link. This never changes the specs we publish.
Preparation
- Park vehicle on level surface and engage parking brake
- Ensure vehicle has been off for at least 30 minutes to allow components to cool
- Verify you have high-voltage safety training and appropriate PPE
- Disconnect the 12V battery negative terminal and wait 2 minutes
- Ensure work area is dry and free of conductive materials
- Review vehicle service manual for high-voltage system layout
Procedure
- 1Remove rear cargo area trim panelsOpen the rear liftgate. Remove the rear cargo floor cover and side trim panels on the driver's side to access the onboard charger location. The charger is mounted on the left side of the rear cargo area behind the trim. Remove any cargo hooks or fasteners securing the trim panels.
- 2Access high-voltage service disconnectLocate the high-voltage service disconnect in the rear cargo area under the load floor. Remove the protective cover by loosening the cover screws. The disconnect is typically marked with a high-voltage warning label.Torque specCover Screws11 Nm (8 lb-ft)
- 3De-energize high-voltage systemWearing high-voltage gloves, grasp the high-voltage service disconnect handle and rotate counterclockwise, then pull straight out to remove. Store the disconnect in a secure location away from the vehicle. Wait minimum 10 minutes for high-voltage capacitors to discharge. Install lockout/tagout device if available.⚠️Do not proceed until 10 minutes have elapsed after removing service disconnect.
- 4Verify zero voltageUsing a high-voltage capable multimeter, verify zero voltage across the high-voltage bus terminals. Measure at the service disconnect connector. Voltage must read below 3V DC before proceeding. Document the reading if required by shop procedures.⚠️If voltage is present, do not proceed. Investigate cause of residual voltage.
- 5Disconnect charging port connectionsLocate the AC input cable from the charging port to the onboard charger. Press the connector release tab and disconnect the AC input connector from the charger inlet. Note the routing of the cable for reinstallation. Tag or photograph wire positions if needed.
- 6Remove high-voltage DC output connectorsWearing high-voltage gloves, locate the DC output connectors (orange cables) on the onboard charger output side. Remove the high-voltage connector bolts securing each connector. Carefully pull the connectors straight off the charger terminals. Cover exposed terminals with insulating caps or tape.⚠️Ensure high-voltage gloves are worn and voltage has been verified as zero before touching orange cables.Torque specConnector Bolts7 Nm (5 lb-ft)
- 7Disconnect communication and sensor connectorsLocate the low-voltage communication harness connectors on the onboard charger. Press the connector lock tabs and disconnect all low-voltage connectors. These typically include CAN bus communication and temperature sensors. Remove sensor bolts if sensors are integrated into the charger.Torque specSensor Bolts11 Nm (8 lb-ft)
- 8Disconnect coolant lines (if equipped)The onboard charger may have coolant lines for thermal management. Place shop towels below connections. Loosen coolant line connector bolts and carefully disconnect lines. Be prepared for minor coolant spillage (typically less than 4 oz). Cap or plug lines and charger ports immediately to prevent contamination.Torque specConnector Bolts7 Nm (5 lb-ft)
- 9Remove charger mounting bracket boltsSupport the onboard charger with one hand or have an assistant hold it. Remove the bracket bolts securing the charger mounting brackets to the vehicle structure. Keep track of all mounting hardware, brackets, and spacers for reinstallation.Torque specBracket Bolts20 Nm (15 lb-ft)
- 10Remove main charger mounting boltsRemove the main mounting bolts securing the onboard charger to its mounting location. Support the charger weight as you remove the final bolts. The charger weighs approximately 30 lbs, so use proper lifting technique.⚠Charger is heavy and awkwardly shaped. Use assistance or proper lifting technique to avoid injury.Torque specMounting Bolts27 Nm (20 lb-ft)
- 11Remove onboard charger from vehicleCarefully maneuver the onboard charger out of its mounting location, ensuring no connectors or brackets are still attached. Watch for sharp edges on vehicle structure. Inspect the mounting area for any debris or damage. Place the old charger on a clean work surface.
- 12Inspect and prepare new chargerInspect the new onboard charger for any shipping damage. Verify part number matches vehicle application. Inspect all high-voltage terminals for damage or contamination. Check that all mounting brackets transfer from old unit if not included with new charger. Inspect coolant ports and connectors for damage.
- 13Install new onboard chargerPosition the new onboard charger into the mounting location, aligning mounting holes with vehicle structure. Install main mounting bolts and tighten to specification. Ensure charger is properly seated and aligned before final torquing. Install bracket bolts and tighten to specification.Torque specMounting Bolts27 Nm (20 lb-ft)Bracket Bolts20 Nm (15 lb-ft)
- 14Reconnect coolant lines and low-voltage connectorsReconnect coolant lines if equipped, ensuring proper seating and tightening connector bolts to specification. Reconnect all low-voltage communication harness connectors, ensuring positive lock engagement. Install any temperature sensors and tighten sensor bolts to specification.Torque specConnector Bolts7 Nm (5 lb-ft)Sensor Bolts11 Nm (8 lb-ft)
- 15Reconnect high-voltage DC connectorsWearing high-voltage gloves, remove insulating covers from terminals. Inspect high-voltage connector seals and replace if damaged. Carefully align DC output connectors (orange cables) with charger terminals and press firmly until seated. Install high-voltage connector bolts and tighten to specification. Ensure proper torque is critical for electrical connection integrity.⚠Proper torque on high-voltage connectors is critical to prevent arcing and overheating. Use calibrated torque wrench.Torque specConnector Bolts7 Nm (5 lb-ft)
- 16Reconnect AC input from charging portReconnect the AC input cable from the charging port to the onboard charger inlet. Ensure connector is fully seated and lock tab engages. Route cable according to original path, securing with cable ties if necessary. Verify no pinch points or interference with moving components.
- 17Reinstall high-voltage service disconnectRemove lockout/tagout device if installed. Align the high-voltage service disconnect with its receptacle and push straight in until fully seated. Rotate clockwise to lock in position. Install protective cover and tighten cover screws to specification.Torque specCover Screws11 Nm (8 lb-ft)
- 18Reconnect 12V battery and clear codesReconnect the 12V battery negative terminal. Using a diagnostic scan tool, clear any high-voltage system DTCs that were set during the procedure. Check for any new fault codes that may indicate installation issues.
Reassembly
- Reinstall all rear cargo area trim panels and fasteners in reverse order of removal
- Ensure all trim panels are properly seated and secured
- Reinstall cargo floor cover and any removed cargo hooks or accessories
- Verify coolant level is correct if coolant lines were disconnected (add ACDelco DEX-COOL if needed)
Verification
- Turn vehicle to ON position and verify no high-voltage system warning lights remain illuminated
- Using scan tool, verify onboard charger communication is established and no DTCs are present
- Plug in a Level 1 or Level 2 charging cable and verify charging initiates normally
- Monitor charging for at least 5 minutes to verify proper operation and no fault codes
- Check for any unusual noises, smells, or warning messages during charging
- Verify charging rate is within normal parameters for the connected charging level
- Inspect all connection points for proper seating and no signs of overheating after initial charging test