steering
Power Steering Gear Box
for 2017 Toyota Corolla 1.8L I4 · FWD
Editorial review:Chris Hackleman — Master Technician · 20+ years · Jeff Moore — Master Lexus & Toyota Mechanic · 20+ years
Difficulty
Advanced
Time
3.5 h
Tools
11
Steps
12
✓Expert-verified. Personally reviewed and approved by OLP's master technicians (Chris Hackleman & Jeff Moore — 20+ years each). Always follow the vehicle's factory service information and torque specs.
This procedure covers the removal and replacement of the electric power steering gear box (rack and pinion assembly) on a 2014-2019 Toyota Corolla with 1.8L I4 engine.
Warnings
⚠️Never turn the steering wheel with the intermediate shaft disconnected or the steering gear removed, as this will damage the clock spring in the steering column.
⚠️Ensure the vehicle is securely supported on jack stands. Never work under a vehicle supported only by a jack.
⚠The steering gear is heavy (approximately 25 lbs). Use proper lifting technique and have an assistant available.
⚠Power steering fluid will spill during line disconnection. Protect painted surfaces and have adequate absorbent materials ready.
ℹ️An alignment will be required after this procedure if tie rods are disconnected from the steering knuckles.
Tools required
Floor jack and jack standsEssential
Torque wrench (10-150 Nm range)Essential
19mm socket for lug nutsEssential
14mm, 17mm, 19mm sockets and wrenchesEssential
Tie rod end separator (pickle fork or ball joint separator)Essential
Steering wheel locking device or bungee cordEssential
Drain pan for power steering fluidEssential
Line wrench set (flare nut wrenches)
Pliers for cotter pin removalEssential
Wire brush for cleaning threads
Turkey baster or fluid transfer pump
Parts
- Power steering gear box (rack and pinion assembly) × 1 — Use OEM specification
- Power steering line O-rings × 4 — Use OEM specification
- Tie rod end cotter pins × 2 — Use OEM specification
- Steering intermediate shaft coupling bolt × 1 — Use OEM specification
Fluids
- Toyota ATF Dexron III — 1 qt
Preparation
- Park vehicle on level ground and set parking brake
- Turn steering wheel to center position and lock it with a steering wheel lock or secure to seat with bungee cord to prevent rotation
- Disconnect negative battery terminal and wait 90 seconds for airbag system to discharge
- Raise front of vehicle and support securely on jack stands placed on frame rails
- Remove both front wheels
- Remove engine under covers and splash shields to access steering gear
- Place drain pan under steering gear area
- Use turkey baster or pump to remove as much power steering fluid as possible from reservoir
Procedure
- 1Remove tie rod ends from steering knucklesRemove the cotter pins from both tie rod end castle nuts using pliers. Loosen but do not remove the castle nuts. Use a tie rod end separator tool to disconnect the tie rod ends from the steering knuckles. Remove the castle nuts and separate the tie rod ends completely. Mark or measure the position of the tie rods on the rack for approximate reinstallation position.Torque specTie Rod End Castle Nut55 Nm (41 lb-ft)
- 2Disconnect steering intermediate shaftFrom inside the vehicle or through the access hole in the firewall, locate the steering intermediate shaft coupling at the base of the steering column where it connects to the steering gear input shaft. Mark the relationship between the shaft and gear for reassembly. Remove the pinch bolt securing the intermediate shaft to the steering gear. Slide the shaft upward off the gear input splines. Do not rotate the steering wheel from this point forward.
- 3Disconnect power steering pressure and return linesLocate the power steering pressure line (high pressure) and return line connections on the steering gear. Place a drain pan below the connections. Using a line wrench if available, carefully loosen and disconnect the pressure line fitting from the steering gear. Remove and discard the O-ring. Disconnect the return line fitting and remove the O-ring. Allow fluid to drain completely. Cap or plug the lines and gear ports to prevent contamination.⚠Power steering fluid will drain from both the lines and the gear. Have absorbent materials ready.Torque specPower Steering Line Fittings30 Nm (22 lb-ft)Pressure Line Fitting32 Nm (24 lb-ft)
- 4Remove steering gear mounting brackets and boltsLocate the two steering rack mounting brackets that secure the gear to the front subframe or crossmember. Remove the mounting bracket bolts on both sides. The brackets may need to be removed separately or may come off with the gear depending on design. Support the steering gear as you remove the final mounting bolt.⚠Support the steering gear before removing the final mounting bolt to prevent it from falling.Torque specRack Bolts97 Nm (71 lb-ft)
- 5Remove steering gear from vehicleWith all mounting bolts and connections removed, carefully maneuver the steering gear assembly out through the wheel well opening on the driver's side. This may require rotating the gear and feeding the passenger side tie rod through the opening first. The gear is heavy, so use proper lifting technique. Inspect the mounting bushings in the brackets for wear and replace if necessary.
- 6Prepare new steering gear for installationRemove the protective caps from the new steering gear ports. Install new O-rings on all power steering line fittings, lubricating them lightly with clean power steering fluid. Ensure the new gear is in the center position by measuring equal tie rod extension on both sides. If tie rods were transferred from the old gear, verify they are at the same position as marked during removal.
- 7Install steering gear into vehicleCarefully maneuver the new steering gear assembly into position through the driver's side wheel well opening. Align the mounting holes with the subframe or crossmember. Install the mounting brackets and bolts finger-tight initially. Ensure the gear input shaft is accessible for intermediate shaft connection before fully tightening.
- 8Torque steering gear mounting boltsWith the steering gear properly positioned and aligned in the mounting brackets, torque the mounting bolts to specification in an alternating pattern to ensure even pressure. Verify the gear can move slightly in its bushings but is securely mounted without excessive play.Torque specRack Bolts97 Nm (71 lb-ft)
- 9Reconnect power steering linesConnect the power steering pressure line to the steering gear, ensuring the new O-ring is properly seated. Hand-thread the fitting several turns to ensure proper engagement. Torque the pressure fitting to specification. Connect the return line with its new O-ring and torque to specification. Verify both fittings are secure and properly aligned.Torque specPower Steering Line Fittings30 Nm (22 lb-ft)Pressure Line Fitting32 Nm (24 lb-ft)
- 10Reconnect steering intermediate shaftAlign the steering intermediate shaft with the steering gear input shaft, matching the marks made during disassembly. Ensure the splines are fully engaged and the shaft is seated completely. Install the new pinch bolt and torque according to manufacturer specifications. Verify the connection is secure and there is no play between the shaft and gear.
- 11Reconnect tie rod ends to steering knucklesInsert the tie rod end studs into the steering knuckle tapers. Install the castle nuts and torque to specification. Install new cotter pins through the castle nut slots and tie rod end studs. Bend the cotter pin ends to secure. Verify both tie rod ends are fully seated in the knuckle tapers.ℹ️If the cotter pin hole does not align after torquing, tighten the nut further (never loosen) until the next slot aligns with the hole.Torque specTie Rod End Castle Nut55 Nm (41 lb-ft)
- 12Fill and bleed power steering systemFill the power steering reservoir with Toyota ATF Dexron III to the cold fill line. Remove the steering wheel lock. With the engine off, turn the steering wheel slowly from lock to lock several times to purge air from the system. Check fluid level and add as needed. Start the engine and turn the steering wheel lock to lock slowly several times while checking for leaks at all connections. Top off fluid to the hot fill line once the system reaches operating temperature.⚠Do not hold the steering wheel at full lock for more than 5 seconds to prevent pump damage.
Reassembly
- Reinstall engine under covers and splash shields
- Install both front wheels and torque lug nuts to specification in a star pattern
- Lower vehicle to ground
- Reconnect negative battery terminal
- Check power steering fluid level after test drive and top off if necessary
Verification
- Start engine and verify no leaks from power steering line connections or gear housing
- Turn steering wheel lock to lock and verify smooth operation with no binding or unusual noises
- Check power steering fluid level with engine at operating temperature
- Test drive vehicle at low speed to verify proper steering response and feel
- Verify no warning lights are illuminated on instrument cluster
- Schedule a professional wheel alignment as tie rod positions may have changed